Dagenham Park School

Client: Barking and Dagenham Schools
Architect: Allford Hall Monaghan Morris
Contractor: Laing O’Rourke
Value: £440k
Duration: 28 weeks

Description
The new 3 storey 10,500m2 school building built on a complex and highly constrained existing school site replaced a number of outdated education buildings enabling an increase in pupil numbers with vastly improved facilities, especially for the School’s specialism in Performing Arts.
SJE Works
SJE completed the supply and fit carpentry fit out package at this ground breaking new school in September 2012, on programme and in budget. Our works included bespoke door sets factory finished in laminate and timber veneer, ironmongery sets, skirting’s, window boards and window linings. We also carried out the washroom fit out, FFE, reception desks, kitchens, work stations, glazed 40DB internal acoustic screens, protection rails and floating acoustic subfloors.